2020,Uzbekistan&32;-&32;220kV&32;Zafarabad&32;Substation&32;and&32;Extension&32;of&32;Syrdarya&32;Substation&32;Project
1.The project owner is the National Electric Grid of Uzbekistanthe implementation of the project started on 21 December 2021 with the construction of One 220kV digital substation occupies about 75000 ㎡ Expansion of 2 line intervals on the opposite side of the station
2.Zafarabad substation is the First Digital Substation in Uzbekistan, Its SCADA system has two-tier architecture of Station Control Layer+Interval Layer, which realizes digital intelligent control of the substation through the IEC 61850 communication standard; The substation is connected to the Syrdarya Thermal Power Plant via a double 220kV line
3.The completion of the Zafarabad substation will provide an additional 400MW of power supply to the Jizzakh region. The completion of the substation will play an important role in improving the power supply to the eastern part of Uzbekistan, doubling the local power supply and at the same time effectively improving safety and reliability, providing a strong guarantee of power supply for the development of the region.
Zafarabad substation is the First Digital Substation in Uzbekistan
Its SCADA system has two-tier architecture of Station Control Layer+Interval Layer, which realizes digital intelligent control of the substation through the IEC 61850 communication standard; The substation is connected to the Syrdarya Thermal Power Plant via a double 220kV line
Contact Us
- Shanghai&32;Electric&32;Power&32;Transmission&32;&&32;&32;Distribution&32;Engineering&32;Co.,&32;Ltd&32;.
Address:4th&32;Floor,No.1395&32;Yu&32;Yuan&32;Rd,Shanghai,PRC
Post code:200250
Tel: 8621-52371666
Fax:8621-52378863